A project announcement tells you where money may eventually be spent.
A contractor award tells you where it's already moving.
This week, some of the strongest signals aren't coming from ribbon cuttings.
They're coming from a roughly $1.25 billion construction program in West Texas, an Amazon generator relationship that could reach $8 billion, a 20-year power agreement in Ector County, an electrical-material award in Ohio, and a mysterious 22-mile gas pipeline being built for a data center nobody has publicly identified.
That's why this week's theme is simple:
Follow the contractor tree.
The earlier you identify who controls the work, the better positioned you are to get downstream of it.
NEED A PROJECT RESEARCHED FOR YOUR COMPANY?
MyDataCenterScout.com — $99 Opportunity Brief
Tell us the market, project, developer or contractor you're trying to understand.
We'll research the opportunity and build a focused brief around:
Project status
Developer/owner
Known contractors
Power strategy
Procurement signals
Contacts
Sources
Potential next moves
One project. One focused research brief. $99.
GET YOUR OPPORTUNITY BRIEF →
THE CONTRACTOR BRIEF
Here are the five things contractors should take away from this week's research.
1. Cedarvale has become a contractor-tree story.
Public filings identify TRINITY Group Construction with a major Ward County data-center construction program.
The bigger question now:
Who sits underneath TRINITY?
We're investigating the electrical, mechanical, civil, controls, commissioning and power infrastructure layers.
2. Amazon is securing infrastructure years ahead.
Generac's new Amazon relationship could involve up to $8 billion in generator purchases.
Separately, Prysmian, Rio Tinto/Elysis and Wesco are already visible in the supply chain for an Amazon data center in Ohio.
Owners aren't waiting until buildings are ready to buy critical infrastructure.
Neither should contractors wait until groundbreaking to start positioning.
3. Power procurement is becoming construction procurement.
Ector County has a 20-year power agreement.
An unnamed West Texas data center is getting 76MW of behind-the-meter generation.
Another undisclosed U.S. campus is getting a dedicated 22-mile gas pipeline.
Project Jupiter's power requirement is measured in gigawatts.
The opportunity increasingly begins outside the data center walls.
4. New Mexico deserves contractor attention.
Google is exploring Lea County.
Project Jupiter is advancing in Doña Ana County.
Those are very different projects at very different stages—but both could create substantial infrastructure and construction ecosystems.
5. Follow the money downstream.
Knowing a $10 billion project exists is useful.
Knowing the GC is better.
Knowing the electrical contractor, mechanical contractor, commissioning firm, equipment suppliers and procurement contacts is where the information becomes actionable.
That's where DCCR is digging.
THIS WEEK'S STRONGEST SIGNALS
🟢 POSITION NOW
Google — Lea County, New Mexico
Early enough that the major contractor tree has not publicly formed.
New Era — Ector County, Texas
Land secured, permits reportedly in hand and long-term Phase 1 power contracted.
🟡 PROCUREMENT / CONSTRUCTION ACTIVE
Cedarvale — Ward County, Texas
Major construction program underway. Subcontractor tree still being mapped.
Amazon / Generac
Multi-year critical-power procurement relationship.
Amazon Ohio
Electrical-material supply chain already emerging.
Kairos / Google
Samsung C&T and Barnard Construction visible in the construction ecosystem.
🔵 INFRASTRUCTURE WATCH
Project Jupiter — New Mexico
Power infrastructure remains central to project execution.
Woodway Mystery Project
22 miles of dedicated natural-gas infrastructure for an unidentified data-center customer.
WANT MORE THAN THIS WEEK'S 8?
Explore the DCCR 25 Project Tracker
The newsletter gives you this week's strongest opportunities.
The 25 Project Tracker gives you the broader pipeline.
We're tracking 25 U.S. data center projects across the development and construction cycle.
Use it to:
Search projects
Filter opportunities
Track project stage
Identify emerging contractor signals
See what DCCR is watching next
OPEN THE 25 PROJECT TRACKER →
8 LEADS THIS WEEK

1 — CEDARVALE / WARD COUNTY, TEXAS
Opportunity Score: HIGH
Project: Cedarvale AI/HPC campus
Location: Ward County, Texas
Site owner: Ionic Digital
Tenant/operator: Nscale
Known contractor: TRINITY Group Construction
Stage: Active construction
This is becoming one of the most interesting contractor-tree investigations we're following.
Ionic Digital says 234MW at its Ward County property is currently leased to Nscale.
Nscale is also contractually obligated to lease another 89MW when that capacity becomes available.
Ionic says it is seeking to expand the property's energy capacity toward 700MW, subject to regulatory approval.
Meanwhile, public construction disclosures identify TRINITY Group Construction with a major Ward County data-center construction program.
PROCUREMENT INTELLIGENCE
TRINITY's business model matters.
The contractor has disclosed that subcontractors perform substantial portions of its construction activity.
That means the opportunity isn't simply:
Who is the GC?
We know that.
The question is:
Who has electrical?
Who has mechanical?
Who has civil?
Who has controls?
Who has commissioning?
That's where we're digging.
DCCR NEXT MOVE
Map the current TRINITY subcontractor tree.
Status: ACTIVE INVESTIGATION
2 — TEXAS CRITICAL DATA CENTER / ECTOR COUNTY
Opportunity Score: HIGH
Developer: New Era Energy & Digital
Location: Ector County / Odessa, Texas
Campus: Approximately 438 acres
Phase 1: Approximately 250MW
Power: At least 207MW contracted
Power provider: Luminant / Vistra
Target delivery: Q3 2027
New Era has secured a 20-year PPA with Luminant, a Vistra subsidiary, supporting Phase 1 of its Texas Critical Data Center.
The power comes directly from Vistra's approximately 1.1GW Odessa natural-gas generation facility adjacent to the site.
New Era says it now has:
Land secured.
Construction permits in hand.
Phase 1 power contracted.
And room for additional phases.
PROCUREMENT INTELLIGENCE
The project is increasingly de-risked from a power standpoint.
The construction tree remains much less visible.
WATCH FOR
GC/CM
Civil/sitework
Electrical
Mechanical
Substation/interconnection
Commissioning
Tenant announcement
DCCR NEXT MOVE
Identify the construction team before major packages become broadly visible.
3 — GOOGLE / LEA COUNTY, NEW MEXICO
Opportunity Score: HIGH
Developer: Google
Location: Lea County, New Mexico
Capacity: Undisclosed
Investment: Undisclosed
Stage: Early development
Google is exploring a potential data-center development in Lea County.
That's interesting precisely because so much remains unknown.
No major GC.
No publicly identified electrical contractor.
No mechanical contractor.
No publicly announced campus capacity.
PROCUREMENT INTELLIGENCE
This is a position-before-procurement opportunity.
WATCH FOR
Land/site control
Utility agreements
Water infrastructure
Civil engineering
Design partners
GC/CM
Substations
Electrical infrastructure
DCCR NEXT MOVE
Track the first companies entering the project ecosystem.
4 — AMAZON + GENERAC

Opportunity Score: HIGH
Customer: Amazon
Supplier: Generac
Initial deliveries: Approximately $2.4B
Potential aggregate purchases: Up to $8B
Initial delivery window: 2027–2028
Amazon and Generac have entered a long-term relationship covering backup generation for Amazon data centers.
Initial deliveries are expected to represent approximately $2.4 billion.
Potential purchases under the relationship could ultimately reach $8 billion.
PROCUREMENT INTELLIGENCE
The manufacturer has been identified.
Now follow the equipment downstream.
Every generator ultimately needs:
Transportation
Equipment setting
Fuel systems
Electrical integration
Switchgear
Controls
Testing
Commissioning
Maintenance
DCCR NEXT MOVE
Identify which Amazon campuses receive the first equipment and which contractors install it.
5 — AMAZON OHIO / PRYSMIAN + RIO TINTO
Opportunity Score: HIGH
Owner: Amazon
Location: Ohio
Cable manufacturer: Prysmian
Material supplier: Rio Tinto / Elysis
Distribution support: Wesco
Specific campus: Undisclosed
Prysmian and Rio Tinto are supplying low-carbon aluminum electrical cabling for an Amazon data center in Ohio.
Prysmian will manufacture the cable in Missouri.
Wesco will support distribution and delivery.
PROCUREMENT INTELLIGENCE
Part of the electrical supply chain is visible.
The installation chain isn't.
WATCH FOR
Specific Amazon campus
GC
Electrical contractor
Switchgear
Transformers
Busway
Controls
Commissioning
DCCR NEXT MOVE
Identify the campus.
Then identify who installs the cable.
6 — PROJECT JUPITER / DOÑA ANA COUNTY, NEW MEXICO
Opportunity Score: HIGH
Tenant: Oracle
Location: Doña Ana County, New Mexico
Planned capacity: Approximately 2.5GW
Stage: Development / construction
Project Jupiter remains one of the largest infrastructure programs we're watching.
Its power requirements are becoming a construction story of their own.
Oracle has reportedly sought significant additional renewable generation in New Mexico while the project's broader power strategy continues developing.
PROCUREMENT INTELLIGENCE
At this scale, changes in power strategy can create major infrastructure packages.
WATCH FOR
Renewable EPC
Transmission
Substations
Natural-gas infrastructure
Onsite generation
Energy storage
Electrical
Civil
Commissioning
DCCR NEXT MOVE
Track how power procurement translates into contractor awards.
7 — KAIROS POWER + GOOGLE / TENNESSEE
Opportunity Score: MEDIUM-HIGH
Developer: Kairos Power
Location: Oak Ridge, Tennessee
Project: Hermes 2
Capacity: 50MW
Known participants: Samsung C&T / Barnard Construction
Potential Google/Kairos program: Up to 500MW
Samsung C&T has joined the integrated EPC ecosystem surrounding Kairos Power's Hermes 2 advanced nuclear project.
Samsung's initial work includes power-generation systems and balance-of-plant.
The significance extends beyond the first 50MW project.
Google and Kairos ultimately envision a larger advanced-nuclear deployment.
PROCUREMENT INTELLIGENCE
Early contractors and suppliers could gain experience relevant to subsequent deployments.
WATCH FOR
Mechanical
Electrical
Specialty concrete
Structural
Piping
Controls/I&C
Fabrication
Commissioning
DCCR NEXT MOVE
Map the emerging balance-of-plant contractor tree.
8 — WOODWAY'S MYSTERY DATA CENTER
Opportunity Score: MEDIUM-HIGH
Pipeline developer: Woodway Energy Infrastructure
Data-center customer: Undisclosed
Location: Undisclosed
Pipeline: 22 miles
Diameter: 30 inches
Target service: H1 2028
Woodway plans to construct, own and operate a 22-mile, 30-inch natural-gas pipeline serving behind-the-meter generation for an unnamed U.S. data center.
The project is expected to enter commercial service in the first half of 2028, subject to regulatory approvals.
The pipeline also includes an option for extension.
PROCUREMENT INTELLIGENCE
A dedicated pipeline of this scale points toward substantial generation requirements.
The opportunity could include much more than pipeline construction.
WATCH FOR
Pipeline construction
Compression
Metering
Civil
Generation EPC
Electrical
Switchgear
Controls
Commissioning
DCCR NEXT MOVE
Identify the customer and location.
THIS WEEK'S BID WINDOW
POSITION NOW
Google — Lea County
Get into the ecosystem before the major contractor tree forms.
New Era — Ector County
Power is contracted. Construction-team identification is now critical.
ACTIVE / PROCUREMENT
Cedarvale
Construction underway. Subcontractor mapping remains the opportunity.
Amazon / Generac
Supply agreement awarded; downstream campus installation work remains to be identified.
Amazon Ohio
Electrical material supply chain forming.
Kairos / Google
EPC ecosystem forming around Hermes 2.
WATCH & MONITOR
Project Jupiter
Massive opportunity, but power strategy remains a major variable.
Woodway
Potentially significant—but identification comes first.
DCCR TAKE
There's a pattern forming.
Data-center procurement is moving earlier and farther upstream.
Owners are securing:
Power.
Generators.
Electrical materials.
Pipelines.
Generation capacity.
And specialist construction relationships before the broader market sees a traditional construction announcement.
For contractors, waiting for a groundbreaking can increasingly mean arriving late.
The better question is:
What has the owner already committed to—and who's next in the chain?
OPPORTUNITY OF THE WEEK

CEDARVALE — WHO SITS UNDERNEATH TRINITY?
The Ward County opportunity isn't interesting simply because a large data center is under construction.
It's interesting because we can see the top of the contractor tree—but not the bottom.
CONFIRMED
Ionic Digital — property owner
Nscale — tenant/operator
TRINITY Group Construction — major construction participant
CONFIRMED HISTORICAL SITE PARTICIPANT
PACK Power
PACK publicly identifies previous electrical work at Cedarvale.
That makes PACK particularly interesting because it already understands the site's electrical infrastructure.
But historical involvement does not establish current involvement.
PROCUREMENT CONTACT SIGNAL
DCCR contacted Richard Green, Senior Vice President of CE&I at PACK Power, this week.
We asked one specific question:
Is PACK currently performing—or has it been awarded—electrical, power infrastructure, controls, commissioning or related work at Cedarvale/Ward County?
At the time this issue was prepared, we had not received confirmation.
That's the type of question we're going to keep asking.
Not:
“Is there a big project?”
But:
“Who's actually getting the work?”
THE 76MW QUESTION
Kodiak Gas Services has separately announced a six-year agreement to provide 76MW of behind-the-meter baseload power to an unnamed West Texas data center.
Kodiak says it will deploy approximately 40 natural-gas reciprocating generation units, including balance-of-plant.
Deployment begins in Q4 2026 and scales into Q1 2027.
Kodiak says:
The customer is a data-center operator.
The operator has an investment-grade hyperscaler customer.
A GPU designer guarantees the data-center lease.
Those clues make Cedarvale worth investigating.
But they don't prove it.
DCCR STATUS:
UNDER INVESTIGATION — NOT CONFIRMED
We will not report Kodiak as a Cedarvale contractor unless we can establish that relationship through a reliable source.
WHO'S GETTING THE WORK?
TRINITY GROUP CONSTRUCTION
Project: Ward County data center
Role: Construction/design-build ecosystem
GENERAC
Customer: Amazon
Role: Backup generation
Potential purchases: Up to $8B
PRYSMIAN
Project: Amazon Ohio
Role: Electrical cable
RIO TINTO / ELYSIS
Project: Amazon Ohio
Role: Aluminum supply
WESCO
Project: Amazon Ohio
Role: Distribution support
SAMSUNG C&T
Project: Kairos Hermes 2
Role: Integrated EPC / balance-of-plant
BARNARD CONSTRUCTION
Project: Kairos
Role: Construction participant
LUMINANT / VISTRA
Project: New Era Ector County
Role: Long-term power supply
POWER WATCH
This may be the most important theme in Issue #004.
WEST TEXAS
Kodiak: 76MW behind the meter.
ECTOR COUNTY
New Era: 207MW+ long-term power agreement.
NEW MEXICO
Project Jupiter: power requirements measured in gigawatts.
TENNESSEE
Kairos/Google: advanced nuclear enters the data-center power equation.
UNDISCLOSED U.S. CAMPUS
Woodway: 22 miles of dedicated gas pipeline.
The old contractor model was:
Shell → MEP → fit-out
The emerging model increasingly looks like:
Generation → pipeline/transmission → substation → campus infrastructure → data center → commissioning
That's a much larger opportunity map.
THE DCCR EVIDENCE STANDARD
Being early only matters if the information is credible.
We separate our intelligence into four categories.
CONFIRMED
Directly disclosed by the owner, contractor, supplier, government agency or another authoritative source.
PUBLIC RECORD
Permits, regulatory filings, securities disclosures, contracts, property records and similar documents.
DCCR RESEARCH
Connections developed by comparing multiple public sources.
UNDER INVESTIGATION
A potentially important relationship where we don't yet have enough evidence to report it as fact.
We're interested in being early.
We're more interested in being right.
NEXT-MOVE BOARD

CEDARVALE
Next move: Identify TRINITY electrical, mechanical and commissioning partners.
ECTOR COUNTY
Next move: Identify GC/CM and civil/site contractors.
GOOGLE LEA COUNTY
Next move: Track land, utility, engineering and first design relationships.
AMAZON / GENERAC
Next move: Identify first recipient campuses.
AMAZON OHIO
Next move: Identify campus and electrical installer.
PROJECT JUPITER
Next move: Follow generation and power-infrastructure awards.
KAIROS / GOOGLE
Next move: Map balance-of-plant subcontractors.
WOODWAY
Next move: Identify customer and project location.
THESE ARE 8 PROJECTS.
WE'RE TRACKING 25.
The DCCR 25 Project Tracker gives contractors a broader view of the projects we're following between newsletter issues.
Search.
Filter.
Track.
Position earlier.
OPEN THE 25 PROJECT TRACKER →
tracker.datacentercontractorreport.com
PROJECT RADAR
These didn't make the locked eight this week—but they're already on the next research board.
ZEO ENERGY + EWYZE
New U.S. platform combining data centers with dedicated microgrids, solar, storage and dispatchable generation.
Trigger we're waiting for: First named U.S. site.
MICROSOFT — UNION CITY, GEORGIA
Expansion activity remains on our radar.
Trigger: New contractor or procurement award.
ALIGNED — SHIPPINGPORT, PENNSYLVANIA
Gigawatt-scale development remains under review.
Trigger: Construction-team or trade-package intelligence.
MARKET SIGNAL
BEHIND-THE-METER POWER IS BECOMING A CONSTRUCTION MARKET
Four developments in this issue point in the same direction.
Kodiak.
New Era.
Woodway.
Project Jupiter.
Grid availability is increasingly influencing where projects get built, how they're powered and which contractors get hired.
Behind-the-meter power can create entirely new scopes:
Gas infrastructure
Generation plants
Battery storage
Microgrids
Switchgear
Substations
Controls
Electrical integration
Commissioning
For contractors accustomed to thinking only about the building envelope and MEP systems, that's worth paying attention to.
The addressable construction opportunity around a data center is getting larger.
WHY DCCR EXISTS
There is already plenty of data-center news.
We're building something different.
Data Center Contractor Report follows the money down the construction chain.
We want to know:
Who owns the project?
Who controls construction?
Who's getting electrical?
Who's getting mechanical?
Who's doing civil?
Who's supplying the equipment?
What hasn't been awarded?
Who should contractors know?
And where can a company still position itself before the opportunity disappears?
That's what we're building every week.
HELP BUILD THE DCCR CONTRACTOR NETWORK
Working on a data-center project?
Know who won a package?
Seen an RFP?
Know who's handling electrical, mechanical, civil or commissioning?
We want to hear from you.
We're looking for:
GC/CM awards
Electrical contractors
Mechanical contractors
Civil/sitework
Commissioning
Controls/BMS
Generation packages
Substations
Equipment procurement
Bid invitations
Vendor-prequalification information
Tips are verified before publication.
COMING IN ISSUE #005
We're already researching the next wave.
We'll continue following:
The Cedarvale subcontractor tree
The Woodway mystery project
Ector County contractor awards
Google's Lea County development
Amazon's generator deployment
New behind-the-meter power projects
New projects entering the 25 Project Tracker
And anything material that breaks before next week's cutoff.
DATA CENTER CONTRACTOR REPORT
Follow the projects. Find the contractors. Get positioned earlier.
William Coit
Publisher
Data Center Contractor Report
Built for the contractors building the AI infrastructure boom.