
Project announcements tell you where billions may be spent.
Contractors need to know something else:
Who controls the work?
Who has the construction contract?
Who is buying the electrical equipment?
Who is building the substations?
Who is installing the cooling?
And when those names aren't public yet:
Where should contractors be positioning now?
That's the focus of Issue #005.
CONTRACTOR BRIEF
Three projects this week show three different stages of the opportunity cycle.
At Goodnight in Texas, the contractor tree is already producing names.
At Delta Forge 2 in Alabama, a 210MW hyperscale project is advancing while major contractor and utility-infrastructure relationships remain worth watching.
And in Jayton, Texas, another $4.8 billion of Crusoe development has entered the pipeline.
Three stages.
One question:
WHERE IS THE MONEY MOVING NEXT?
STRONGEST SIGNALS THIS WEEK
WORK ALREADY FLOWING
Google / Crusoe — Goodnight, Texas
POSITION NOW
Applied Digital — Delta Forge 2, Alabama
GET ON THE RADAR
Crusoe — Project Hyper, Jayton, Texas
PROCUREMENT WATCH
Colovore — Fort Worth, Texas
EARLY POSITIONING
Lambda — Chouteau, Oklahoma
GRID MONEY
DOE SPARK
POWER CONSTRUCTION
Fervo — Cape Station, Utah
CAPITAL WATCH
Samsung / Helix Digital Infrastructure
8 PROJECTS IN THIS ISSUE.
25 PROJECTS IN THE TRACKER.
The newsletter gives you the projects we're investigating most closely.
The DCCR 25 Project Tracker helps you monitor more opportunities between issues.
Search projects.
Filter opportunities.
Identify where your company should dig deeper.
OPEN THE DCCR 25 PROJECT TRACKER
LEAD #1
GOOGLE + CRUSOE — GOODNIGHT
Armstrong County, Texas
DCCR PRIORITY: HIGH
Google is the customer.
Crusoe is the developer.
But that's where most project announcements stop.
DCCR kept going.
Crusoe broke ground on the Goodnight campus in June 2025.
The campus connects directly with two adjacent wind projects:
Goodnight 1 — 265.5MW — Operational
Goodnight 2 — 265.5MW — Under Construction
Combined:
531MW
But the contractor story extends far beyond the wind projects.

FOLLOW THE CONTRACTOR TREE
GOOGLE
Customer
↓
CRUSOE / GN DC1
Developer / project structure
↓
DPR CONSTRUCTION
Major construction delivery
SOUTHLAND INDUSTRIES
Mechanical / design-build
ROSENDIN
Electrical
↓
BLACK & VEATCH / OVERLAND CONTRACTING
Power-generation engineering and field-construction activity
↓
PACK POWER
Substation EPC
↓
PROENERGY
13 PE6000 turbine-generator packages
Goodnight is becoming much more than a data center construction project.
It is a:
DATA CENTER + GENERATION + SUBSTATION + ELECTRICAL INFRASTRUCTURE PROGRAM.
THE POWER PACKAGE
DCCR research has identified an approximately 700MW active power-generation program developing alongside the campus.
PROENERGY has confirmed an order from Crusoe for 13 PE6000 turbine-generator packages, representing approximately 650MW of generating equipment.
Project-specific records also reference 7 Dynamis DT46 trailer-mounted turbine units.
DCCR has not yet located equivalent direct confirmation from Dynamis.
EVIDENCE STATUS: UNDER INVESTIGATION / HIGH CONFIDENCE
And an important distinction:
Google is confirmed as the Goodnight data center customer. DCCR has not established that Google has contracted for the natural-gas generation project itself.
WE'RE STILL CHASING
Gas supply / pipeline
SCR / emissions systems
Electrical balance-of-plant
Transformers / switchgear
Plant controls
Cooling installation
Commissioning / startup
Additional specialty subcontractors
DCCR NEXT MOVE
Keep moving down the contractor tree.
WHO'S GETTING THE WORK?
GOODNIGHT
DPR Construction — major construction delivery
Southland Industries — mechanical / design-build
Rosendin — electrical
Black & Veatch / Overland — power-generation engineering / field-construction activity
PACK Power — substation EPC
PROENERGY — turbine-generator equipment
Dynamis — additional generation equipment indicated; direct confirmation still under investigation
Goodnight is exactly why DCCR follows contractor relationships—not just project announcements.
FIND THE OPPORTUNITY BEFORE EVERYONE ELSE DOES
Knowing a project exists is useful.
Knowing who controls the work, what stage procurement is in and where your company might fit is better.
My Data Center Scout provides a focused Opportunity Brief on a project you want investigated.
$99 OPPORTUNITY BRIEF
We dig into:
Project status
Owner / developer
Known contractors
Procurement signals
Power infrastructure
Open contractor questions
Positioning opportunities
GET AN OPPORTUNITY BRIEF
LEAD #2
APPLIED DIGITAL — DELTA FORGE 2
Brookwood, Tuscaloosa County, Alabama
DCCR PRIORITY: HIGH
If Goodnight shows where the money has already moved, Delta Forge 2 shows where important relationships remain worth watching.

PROJECT PROFILE
Investment: $3.2B+
Critical IT load: 210MW
Customer: investment-grade U.S. hyperscaler
Lease: approximately 15 years
Base contracted revenue: approximately $5.2B
Delivery target: first half of 2028
Applied Digital describes Delta Forge 2 as a single 210MW building under construction.
The full critical IT load is contracted.
Demand isn't the question.
EXECUTION IS.
WHAT WE KNOW
Developer: Applied Digital
Project entity: APLD BHM-01 LLC
Civil engineering / permitting: Kimley-Horn
Utility: Alabama Power
WHAT WE'RE WATCHING
GC / construction management
Civil / sitework
Electrical
Mechanical
Cooling
Controls / BMS
Commissioning
Substation / transmission
Major equipment suppliers
Applied Digital's Brookwood construction organization references work involving GC coordination, primary subcontractors, GMP negotiations, vendor procurement, owner-furnished equipment and utility coordination.
That's the signal.
THE SECOND CONTRACTOR TREE
At 210MW of critical IT load, the opportunity doesn't stop with the building.
APPLIED DIGITAL
↓
ALABAMA POWER
↓
TRANSMISSION / SUBSTATION / DISTRIBUTION
↓
CAMPUS
DCCR POSITION
POSITION NOW
We're watching for major contractor, trade and Alabama Power infrastructure awards.
OPPORTUNITY OF THE WEEK
DELTA FORGE 2
Why Delta Forge 2?
Because DCCR wants to identify opportunities before every box in the contractor tree is filled.
The project has:
$3.2B+ of investment
210MW of contracted critical IT load
A long-term hyperscaler customer
Construction underway
But publicly, significant pieces of the construction and utility tree remain incomplete.
That doesn't mean those contracts haven't been awarded.
It means we don't yet have sufficient public evidence to responsibly put names in those boxes.
And that's exactly why we're watching.
LEAD #3
CRUSOE — PROJECT HYPER
Jayton, Texas
DCCR PRIORITY: HIGH
Another major Texas project entered the pipeline this week.
Crusoe has filed plans for two data center buildings in Jayton.

Building 1: approximately 759,260 sq. ft.
Building 2: approximately 759,260 sq. ft.
Combined: approximately 1.52 million sq. ft.
Estimated construction cost: $4.8B combined
Target construction start: January 2027
The filings identify the developments as Project Hyper spur buildings.
For contractors, January isn't far away.
We're now looking for:
GC / construction manager
Architect / engineering
Civil / sitework
Electrical
Mechanical
Cooling
Power infrastructure
Commissioning
Long-lead equipment
DCCR POSITION
GET ON THE RADAR
LEAD #4
COLOVORE — ALLIANCE
Fort Worth, Texas
DCCR PRIORITY: HIGH
Colovore is planning a high-density, liquid-cooled facility in Fort Worth's Alliance corridor.
Estimated construction: $430M
Size: approximately 156,500 sq. ft.
Data halls: 4
Capacity: approximately 32MW
Design: Ci Design
Construction start: December 2026
Liquid cooling makes the mechanical side particularly interesting.
WATCH
GC / construction manager
Mechanical
Liquid-cooling distribution
Piping
Electrical
Controls / BMS
Commissioning
Utility interconnection
DCCR POSITION
PROCUREMENT WATCH
LEAD #5
LAMBDA — OKLAHOMA AI DATA CENTER
Chouteau, Oklahoma
DCCR PRIORITY: HIGH
Lambda is developing a new AI data center at MidAmerica Industrial Park.
Up to 1,000 construction workers could be required during development.
Two names already give us the beginning of the infrastructure tree:
Cloverleaf Infrastructure
Grand River Dam Authority — GRDA
Cloverleaf is involved in preparing the property.
GRDA sits on the power/infrastructure side.
WATCH
GC
Civil / sitework
Electrical
Substation / transmission
Mechanical
Cooling
Fiber
Controls
Commissioning
DCCR POSITION
EARLY POSITIONING
LEAD #6
DOE SPARK
Follow the Grid Money
DCCR PRIORITY: HIGH — POWER WATCH
Approximately $1.9B in federal funding is moving toward grid projects through DOE's SPARK program.
Combined with recipient investment, the projects represent roughly $5.25B.
DOE says the program could unlock more than 23GW of additional grid capacity.
For contractors, that means potential work in:
Transmission
Reconductor projects
Substations
Grid-enhancing technologies
Electrical equipment
Engineering
Controls
Commissioning
DCCR's job now is to turn the funding announcement into something more useful:
Named utilities. Named EPCs. Procurement dates. Vendor routes.
LEAD #7
FERVO — CAPE STATION
Beaver County, Utah
DCCR PRIORITY: MED-HIGH
Initial geothermal power is coming online at Cape Station while another 400MW advances through construction.
Google has contracted for a significant portion of future output.
The contractor opportunity sits upstream:
DRILLING
↓
GENERATION
↓
ELECTRICAL BOP
↓
TRANSMISSION
↓
INTERCONNECTION
DCCR POSITION
POWER CONSTRUCTION WATCH
LEAD #8
SAMSUNG + HELIX DIGITAL INFRASTRUCTURE
DCCR PRIORITY: MEDIUM
Samsung has committed $1 billion to Helix Digital Infrastructure.
Helix has secured more than $10 billion in capital commitments.
Samsung also brings capabilities extending beyond capital into areas including construction, cooling and energy storage.
What we don't have yet is the piece DCCR really wants:
A NAMED U.S. CAMPUS.
Until then, this remains an upstream capital and procurement signal.
DCCR POSITION
WATCH FOR THE FIRST PHYSICAL PROJECT
BID WINDOW
WHERE SHOULD CONTRACTORS BE WATCHING NOW?
POSITION NOW
Delta Forge 2 — Alabama
Watch major contractor, trade and utility-infrastructure relationships.
Project Hyper — Texas
January 2027 construction target. Watch GC, civil, MEP and long-lead equipment.
Colovore — Fort Worth
December construction target. Watch GC, mechanical and liquid-cooling packages.
Lambda — Oklahoma
Watch campus construction plus Cloverleaf/GRDA infrastructure.
FOLLOW THE ACTIVE MONEY
Goodnight — Texas
Watch generation BOP, gas infrastructure, controls, emissions and commissioning.
NEXT PROCUREMENT WAVE
DOE SPARK
Watch utility solicitations and EPC packages.
Fervo — Utah
Watch generation and electrical infrastructure.
Samsung / Helix
Watch for the first named U.S. campus.
DCCR TAKE
THE CONTRACTOR WINDOW OPENS BEFORE THE CRANES ARRIVE
Waiting for a groundbreaking is increasingly too late.
The useful signals often appear earlier:
Land acquisition
Large-load utility agreements
Environmental permits
Owner construction hiring
GC RFPs
Equipment orders
Substation filings
Generation permits
Transmission upgrades
Long-lead procurement
Those signals tell you something the groundbreaking doesn't:
THE MONEY IS STARTING TO MOVE.
By the time the cranes appear, somebody may already have the contract.
POWER WATCH
THE PROJECT DOESN'T END AT THE METER
Look at this week's construction chain:

GENERATION
↓
PIPELINES / FUEL
↓
TRANSMISSION
↓
SUBSTATIONS
↓
CAMPUS ELECTRICAL
↓
DATA CENTER
↓
COMMISSIONING
Goodnight combines data centers, wind, substations and behind-the-meter generation.
Delta Forge 2 brings a 210MW load into Alabama Power's infrastructure system.
Fervo is constructing hundreds of megawatts of geothermal generation.
SPARK is directing billions toward grid infrastructure.
If your company only watches the data center building, you're watching only part of the market.
EVIDENCE STANDARD
CONFIRMED
Supported directly by a company announcement, filing or equivalent primary source.
PUBLIC RECORD
Supported by permits, regulatory filings or government documentation.
DCCR RESEARCH
Supported by credible project-specific evidence assembled by DCCR.
UNDER INVESTIGATION
A credible lead that isn't ready to be stated as established fact.
We want to be early.
We want to be right more.
NEXT-MOVE BOARD
GOODNIGHT
Gas infrastructure • electrical BOP • emissions • commissioning
DELTA FORGE 2
GC • primary trades • Alabama Power infrastructure
PROJECT HYPER
GC • design team • civil • MEP
COLOVORE
GC • mechanical • liquid cooling
LAMBDA
Cloverleaf scope • GRDA packages • GC
DOE SPARK
EPC awards • procurement dates • vendor routes
FERVO
Electrical BOP • transmission • commissioning
SAMSUNG / HELIX
First U.S. campus
8 PROJECTS THIS WEEK.
25 IN THE TRACKER.

The newsletter gives you the projects we're investigating most closely. The DCCR 25 Project Tracker helps you monitor more opportunities between issues.
OPEN THE DCCR 25 PROJECT TRACKER
PROJECT RADAR
SKYBOX + PROLOGIS — HUTTO, TEXAS
A fourth building has surfaced at the Hutto campus.
STATUS: WATCH
AKAMAI + ANTHROPIC
Massive compute commitments. Physical deployment locations still needed.
STATUS: WATCH
SCHNEIDER ELECTRIC — LIQUID COOLING
High-capacity liquid-cooling technology with future U.S. procurement implications.
STATUS: PROCUREMENT WATCH
ZEO ENERGY + EWYZE
Interesting off-grid model. Waiting for the first identifiable physical project.
STATUS: WATCH
MARKET SIGNAL
FIND THE PROJECT BEFORE THE TREE IS FULL.
The sequence increasingly looks like:
CAPITAL
↓
LAND
↓
POWER
↓
PERMITS
↓
PROCUREMENT
↓
CONTRACTORS
↓
CONSTRUCTION
The earlier you enter that sequence, the more useful the intelligence becomes.
WHY DCCR EXISTS
There are excellent publications covering data center growth.
DCCR asks a narrower question:
WHO GETS THE WORK?
And when those names aren't public yet:
WHO SHOULD CONTRACTORS BE WATCHING?
That's why we follow permits, utility filings, equipment orders, construction hiring and subcontractor relationships.
A billion-dollar announcement is interesting.
A billion-dollar project where you understand who controls the work is useful.
CONTRACTOR NETWORK
HELP US FILL THE TREE
Working on one of these projects?
Know who received a package?
Have intelligence on:
GC / CM awards
Civil / sitework
Electrical
Mechanical
Cooling
Controls / BMS
Commissioning
Substations
Generation
Equipment procurement
Bid invitations
Vendor prequalification
Send it to DCCR.
We verify before we publish.
COMING IN ISSUE #006
We're continuing to investigate:
Delta Forge 2 contractor awards
Project Hyper construction team
Goodnight power-generation packages
Alabama Power infrastructure
Colovore's liquid-cooling construction team
Lambda's Oklahoma contractor tree
Helix's first U.S. campus
And whatever moves next.
DATA CENTER CONTRACTOR REPORT
Projects. Contractors. Opportunities.
William Coit
Publisher
Built for the contractors building the AI infrastructure boom.

